| Ellerbe Becket Quarterly, Volume 1, Number 2
Taking Teamwork To New Heights
Collaboration fills a tall order
When construction is completed in 2001, Hae Song Plaza will be the tallest building in Inch’on, South Korea.
At 40 stories and three million square feet (278,700 m2), the office/hotel/retail complex is also one of the
largest construction projects in the world. “An international project of this magnitude usually would go
through several years of negotiating and planning,” said Kyun Kim, project director and client liaison (San
Francisco). “But within 90 days of our first conversation with the chairman of Hae Song Limited, we started
work on concept studies for this project.”
Hae Song Limited awarded Ellerbe Becket the office and retail complex in February 1996. By June
negotiations concluded, and programming and master planning began.
The project presented clear challenges—geographically, structurally and logistically. Hae Song Plaza is
located about 25 miles (40 km) west of Seoul, outside the historical center of Inch’on, in an area that was
filled with storage yards and shipping stations. Besides considering Korea’s current experimentation with
architecture and technologies, designers had to anticipate the urban landscape’s development and blend
their design with the natural beauty of nearby Inch’on Harbor. “It challenged our firm to design a worldclass
complex that would become a city icon,” said Michael D. Jones, overall design principal (Washington,
D.C.).
Hae Song Plaza comprises an office building, 550-room, five-star hotel, department store, shopping center
and 2,700-car underground garage. The total project size is about 278,000 square meters—more than three
million square feet. “Early on it became apparent that the project was too large for any single team in the
organization,” said Jones.
For one firm to provide effective design as well as project and construction management would be an
intricate task, even without the additional hurdles of distances between offices, varying time zones and
differing languages. But strong interoffice collaboration and the right people with the right expertise can fill
a tall order.
Rounding up the best people
Jones had just relocated from New York to Ellerbe Becket’s Washington, D.C., office and was building a staff
while starting up the Hae Song Plaza project. Although he knew one office couldn’t provide the vast
experience needed, a combination of locations might offer the architectural, engineering and construction
services knowledge necessary to get the project off the ground. “It was our desire to take advantage of
Ellerbe Becket’s multidisciplinary approach,” Jones explained.
The trick was to identify personnel, regardless of their locations, with the appropriate expertise for the
project. It took six months to gather all of the people from all of the disciplines and offices who would guide
the project to success. For example, high-rise design, curtain wall systems and master planning came from
Washington, D.C. Kansas City, Mo., furnished knowledge about major project delivery and large team
management. Retail design resided in San Francisco. And Minneapolis supplied lighting design and
construction management. “About 10 percent of the entire company had a role in Hae Song Plaza,” said
Barry Huhn, overall project architect (Kansas City). “Each person from every location was an invaluable
member of the team.”
At the beginning, Kim and Jones built the team around several key requirements. Structural engineering, for
example, was one of the biggest considerations. Deep, waterproof foundations were necessary to hold back
the water table. And the slender office building’s frame needed bracing to withstand hurricane-force winds.
Because the project required two engineers that had built work of at least 40 stories in height, H.B. Warner
(Kansas City) and Ramesh Desai (Washington, D.C.) joined the team.
To coordinate the process and the people involved, strong project leadership was critical. Hae Song’s overall
project director had to have experience with built work in excess of US $100 million in construction costs.
Due to his solid experience with large projects, developer clients and commercial office buildings, Doug
Smith (Kansas City) came on board the growing team. “Doug’s presence in the Kansas City office
complemented the selection of H.B. as one of the structural engineers,” explained Jones. “It provided a
platform for locating part of the project in Kansas City.”
Shore-to-shore collaboration
Early on the team decided to split up the architectural work by its major components—office building, hotel,
atrium and retail. Strategically, said Jones, it made sense to put the office building work in Washington,
D.C., given that location’s recent experience with office buildings and mid-rise towers. Senior designer David
Rova had recently completed design work on the 39-story Karet Office Tower in Jakarta and on the glass
curtain wall for the New York Psychiatric Institute. In addition, the office led master planning, programming
and schematic design, and performed all mechanical, electrical and plumbing engineering design.
The team put the hotel work in the good hands of Kansas City’s architecture and interiors staff. The office
collaborated with Washington, D.C., for the schematic design process as well.
At the start of the design development phase the San Francisco office came on board to handle design of the
department store, shopping center and seven-story atrium.
Jones directed the master planning effort of the core team, with Huhn providing assistance from the Kansas
City office. “I was doing a lot of commuting back and forth to Washington,” Huhn said.
With his previous experience on mixed-use facilities and projects in Asia, Huhn became indispensable to the
Hae Song Plaza team, said Jones. Besides being project architect for the garage and site, Huhn established
himself as the clearinghouse for all information flowing between team members in the various offices as well
as between Ellerbe Becket and the client.
Each office had its own management and team for its portion of the work. The three primary office leaders
were Rova in Washington, D.C., Sandra Beck in San Francisco, and Huhn in Kansas City. As overall project
director, Smith determined team organization, contract administration, individual responsibilities, scheduling,
due dates, deliverables and the use of technology. “Doug very clearly defined virtually every aspect of the
project and gave very clear direction to the team,” said Jones.
Logistics—the key to success
The architects, engineers, interior designers and countless others couldn’t have maintained organization of
the Hae Song Plaza project without constant communication. Roger Claar, senior project architect (Kansas
City), along with Smith, Rova, Kim and Huhn set the work plan, then held regular team meetings to monitor
progress. “We were continually updating the work plan,” said Huhn. The spreadsheet format tracked tasks,
assignments and deliverables for everyone involved. Project office leaders divided planning into stages that
coincided with client presentations, held about every six weeks. They revisited project plan elements at these
times.
Differing time zones complicated communication with clients in Korea, but the team worked around it. “The
fact that they are a half-day ahead of us allowed us to send them questions at the end of the day and
receive answers by the next morning,” said Jones. They transmitted drawings, memos, correspondence and
other project communications by fax, Lotus Notes<) and express mail.
Having many locations involved made clear, timely, interoffice communication a necessity. Drawings and
images were transmitted between offices via the wide area network or fax. The team also used video
conferencing to view drawings and review interoffice issues.
About every three weeks everyone attended an in-house meeting in Washington, D.C., Kansas City or San
Francisco to review overall issues. “The pace of meetings was often grueling, but it was necessary to keep
the project moving forward on schedule,” said Jones. The meeting locations were determined based on 1)
which elements of the project needed the most attention at the time; 2) a desire to include all team
members in the process; and 3) which locations would logistically keep the least number of people away
from critical tasks they needed to be working on in their own offices.
Kim, who acted as client liaison, said Hae Song Limited’s main concern was not where the work was done,
but that it was completed and high quality. The team held meetings with clients every six to eight weeks in
Washington, D.C., San Francisco or New York, and gave a few major presentations in Seoul. Between
regularly scheduled meetings, Jones, Smith, the lead engineers and others made trips as needed. “It seemed
like Doug Smith and I were on airplanes all of the time,” Jones said.
Clear organization and information ensured a smooth transfer of the project to local Korean architects and
engineers after the design development phase. The Ellerbe Becket team handed over the entire project file in
electronic format—including drawings, notes, specifications, calculations and cost estimate data—to their
Korean counterparts.
Working together through technology
Software created three-dimensional models that enabled the team to do in-depth analysis of design plans
and options. Realistic imagery helped explain concepts to the Korean client by simulating the experience of
walking through spaces.
Computer-aided design (CAD) experts including Bryce LaMar (Kansas City) and architect Kurt Amundsen
(Kansas City) resolved production issues. The team charged Amundsen with ensuring that project drawings
were checked into the electronic library every day, formatted properly, and used the right structural grid.
“This was an all-consuming job in itself,” said Jones, though Amundsen also was responsible for parts of the
design and production work.
After coordinating interoffice standards for formatting, numbering and setting up CAD files, Amundsen and
LaMar documented, distributed and “policed” the processes. “Setting and following strict CAD file
management guidelines is absolutely critical to a project of this complexity,” said Doug Smith. “One layering
mistake in a drawing can mess up 20 drawings where it’s referenced.” Despite the complexity and
somewhat experimental nature of the work process, Smith said, “The team really pulled together and
overcame some amazing obstacles to make the process work.”
When San Francisco came on board and the project was better defined, the interoffice team had to carefully
delineate which drawings would be done where, and then set clear match lines to which the project pieces
would be aligned. “Working around these match lines was a major coordination issue up to the end of the
process,” said Jones. Each office generally produced its own package of drawings and coordinated the
structural and mechanical/electrical/plumbing components within it.
The team established a standard directory setup that all offices used. Because it slowed the system to have
all offices access CAD files from one server, Information Systems in Minneapolis copied all of the plan
information from each office every night, so that every day each discipline could reference up-to-date project
information. Once a week, all files were copied so that each office’s computer drive contained identical
information.
The team also set up a common directory in which to work on specifications. Kansas City performed the final
edit and published the combined work. “Although it was slow, it was tolerable, and avoided the problem of
having multiple versions of the same document out there with no idea of which one contained all the latest
comments,” explained Huhn.
Technologically the process wasn’t always smooth, admitted Jones. “There was a firmwide CAD upgrade
going on and, as a result, we had to learn a new system at the same time that we were trying to figure out
how to work together at a distance.”
Cooperative learning
The process of coordination, design and management created a facility destined to become a distinguished
Inch’on landmark, according to those involved. But the project was not without challenges in cooperation,
especially since many of the team members hadn’t worked with each other before Hae Song Plaza. “It took
a while for each of us to become more comfortable with one another,” said Jones.
Huhn agreed, “In the beginning of the project, we didn’t know each other.” He said they resolved the
wariness some people felt by defining roles and responsibilities, working together closely and holding
numerous coordination charrettes. “Most important,” Huhn said, “were the open communications, like
copying everybody on all correspondence. We found on occasion that an issue affected a discipline when it
hadn’t even occurred to us that they’d have an interest in the subject. It disproved the idea that there would
be too much paper floating around.”
Kim attributes much of the project’s success to a combination of an enthusiastic client, creative design and
effective management between Ellerbe Becket offices. “In the 35 years of my career, I have not experienced
a project that proceeded this smoothly,” said Kim.
One firm, many people, one process
A century ago Hae Song Plaza would have come together with an altogether different work process—minus
the e-mail, video conferencing and 3-D software.
But not everything has changed. Just like the master builder who served as architect, engineer and builder,
the integrated approach brought many people together in one firm that assumed responsibility for every
project aspect. Hae Song Plaza is the result of a comprehensive team of architects, engineers, construction
services personnel and other professionals that understood and structured itself to meet the owner’s needs.
For Hae Song Ltd., integrated services meant cost effectiveness and one contract. For the team,
responsibilities and communication were clear. Everyone was focused under a single leadership structure,
with one set of goals throughout the project.
The project’s success illustrates the importance of bringing in the right people at the right time—before the
design is complete. “We had a very strong and dedicated team on the Hae Song Plaza project,” said Michael
D. Jones, design principal. “They worked together very well and, at the end, accomplished more than we
ever thought possible in a very short amount of time.”
The team achieved the owner’s specific objectives by inviting participation and open communication. Jones
said the clients generally knew what they wanted and made decisions on time, which contributed to the
project’s success. “We had a very demanding, but very good client with a very good eye, who insisted on
top-quality design,” said Jones. “The extremely dedicated and directed client team actively sought our
advice on issues.”
Update on developments
Ellerbe Becket continues to manage the construction process, which is being completed by a local associate
with knowledge of Korean building codes and materials procurement. Hae Song Plaza’s structural team
developed a system for “top-down construction”; after the perimeter foundation walls and grade-level
working slab are completed, construction occurs simultaneously above and below ground—saving money
and time. In the case of Hae Song Plaza, completion will be a year earlier than is typical for high-rise
projects.
Hilton Hotels recently signed on with Hae Song Plaza, and Ellerbe Becket currently is working with the new
tenant on the design of the hotel component to ensure their requirements are accommodated.
Nearby, construction is underway on a new airport. The airport will handle international flights, making
Inch’on another port of entry into South Korea. The first flights are scheduled to land in 2002; the entire
complex is slated to be completed in 2012. Hae Song Plaza is approximately five kilometers (three miles)
from the airport and will be on a direct route for passengers leaving the island for Seoul.
Taking Teamwork To New Heights is copyright Ellerbe Becket Inc.
All rights reserved. This article may be printed out for personal use. Any public use such as linking,
framing, reposting or reprinting, requires permission from Ellerbe Becket. Please send the request,
including the article title and proposed use to: info@ellerbebecket.com, by fax to +1 (612) 376 2271, or by mail to
Ellerbe Becket, 800 LaSalle Ave., Minneapolis, MN 55402 USA.
|