Project Data
Size (sq ft):
- 14,000 sq ft
Size (sq m):
- 1,301 sq m
Integrated Team:
- Interiors: Ellerbe Becket
- Engineering: Ellerbe Becket
- Console Design: Evans Consoles
- Audio-visual: Paoletti Associates
- Construction: M.A. Mortenson
The energy utility's new control center achieved two goals: cut costs and improve customer service. The project consolidated five 24-hour operations centers, creating a highly secure emergency operations center that can control the entire one-million-customer power network within 10 minutes of an outage.